Intro to Order Planning

The Order Planning is the main feature of Sequor MTC, as it is responsible for creating, editing, executing and managing Work Orders.

Work Order is a manufacturing document, which is responsible for

specifying the conditions to execute something.

Work orders are classified into:
- Service order (used in *Maintenance* or *Job Management* process)
- Production order (used in the *Manufacturing* process)
- Inspection Order (used in the *Quality* process)
- Transfer order (used in the *Logistics* process)

Different types of order have particular behaviors, but the structure is always the same. but why ??? This is because these business areas are naturally similar. So much so: Maintenance, Manufacturing, quality and logistics are the four pillars of ISA 95 (International Standard provided by the International Society of Automation).Work orders are made up of blocks of information:- What to do - How to do - what to consume - what to expect For more conceptual explanations: https://www.isa.org/ https://en.wikipedia.org/wiki/Work_order

How to create a new MTC Work Order

How to create an Order Header entry:

Sequor Platforma Site

To Create, click on the button and then fill in the fields:

  • Order Number: Number will be suggested, but the user can insert another info. But this field is unique, so if any order number is used, the user needs to inform another one.
  • Order Description: The user can inform a description to the service order.
  • Equipment: The user can select what's the equipment where will be executed the order.
  • Order Type: The user can select what's the type of the service order.

Sequor Platforma Site

remarque

After accessing the Order Header Sequor MTC app, the user will enter the Grid / List mode, which lists all Order Header etries, giving the user the possibility to create a new entry or edit an existing one.

To finish the Order Header Creation process, we have 3 possibilities:

  • 1 – Create Order , only saves the registered data and leaves the entry available to be Dispatched or Completed
  • 2 – Create and Change , in addition to saving the order data, it opens it in Order Completion mode, being possible to complement all the information necessary for the execution of the Order.
  • 3 – Copy from and Change , copies the data in the order indicated in the Copy from field and opens it in Order Completion mode, being possible to complement all the information necessary for the execution of the Order.

How to edit an Order Header entry:

  • It is not possible to edit Order Headers.

How to edit a new MTC Work Order

  • 1 - select the desired entry by clicking on the respective check box ,
  • 2 - click on the button and then fill in the fields according to your process needs.

Sequor Platforma Site

remarque

After accessing the Order Header Sequor MTC app, the user will enter the Grid / List mode, which lists all Order Header entries, giving the user the possibility to create a new entry or edit an existing one.

What is the first step with a created work order?

With the order created, the first step is to fill in all the general information. In the General Information Guide:

Fill in the fields:

  • 1 – Notification Code,
  • 2 - External Order Number,
  • 3 - Parent Order Number,
  • 4 - Workcenter
  • 5 - priority

Sequor Platforma Site

  • 6 - You can add a Long Description to the Order by clicking on the button. The Long description has an extensive range of Text tools, links and more. Explore!

Sequor Platforma Site

Sequor Platforma Site

remarque

At any time, you can click on the Update Order or Save and Schedule buttons respectively, save the updates completed so far or save and schedule the order.

OK, my work order header is ready, now what?

After filling in the header information, the next step to filling the work order is to create the operations within it.

But what is an operation?

*Operation* is a sequence of tasks that guides the worker *how to proceed*

Sequor Platforma Site

So how can I insert an operation?

Sequor Platforma Site

On the Operations guide: Fill in the fields:

  • 1 - Short Text,
  • 2 - You can add a Long Description to the Operation by clicking the button
  • 3 - Work
  • 4 - Work Unit
  • 5 - Duration
  • 6 - Unit Normal Duration
  • 7 - WK.F
  • 8 - A.WORK
  • 9 – Functional Location
  • 10 - Workcenter

Copy from

The Copy From functionality aims to optimize the data filling process in cervicer orders. The purpose of this function is to copy data that already exists and use it in other applications.

Copy From - Edit

In the order Edit screen, there is the “Copy From” option, where it is possible to copy an existing order with its data, not needing to enter all the information.

When hovering the mouse on the will appear :
By clicking on the icon shown, it is possible to copy all operations in a specific order. When clicking on the icon, the list of order to be copied will appear.

Sequor Platforma Site

Then select the check box of the desired order and click on the button.

By clicking on the icon indicated , it is possible to copy the desired operations of an order.

When clicking on the icon, the list of order to be copied will appear.

Sequor Platforma Site

Then select the desired operations checkbox and click the button.

danger

This functionality similarly extends to operations data. You can copy information from: material code, personnel number, PRT code, Classes and Equipment number.

Synchronization of download orders

In order to view orders on mobile, you need to download them. After clicking on the sync app, select the option and click in . The orders related to the person responsible will automatically appear. You can select all orders or just the one you want, click in . After click on .

Sequor Platforma Site

Synchronization of upload orders

After performing the activity and registering on mobile, you must upload so that the information is on the web. After clicking on the sync app, select the option . The list of orders that are on mobile will appear. You can select the orders that are complete and want to upload them. You can select all orders or just the one you want, click in . After click on .

Sequor Platforma Site

Operation guide

In the operation guide, the user will find all the steps to execute the service order. Following these steps will complete the perfect workflow.

Sequor Platforma Site

Nr.FieldDescriptionSample
1 Sequence of Operation Sequence of Operation 0010
2 Short text Insert the operation name Open the electrical panel
3 Long Description Insert with a long description (using the draft tool)
4Work Insert the amount of work spent 3
5 Unit of Work Select work unit of measure Hours
6Activity DurationInsert the amount of Activity Duration2
7Unit Normal DurationInsert the amount of Unit Normal Duration2
8WorkflowInsert Workflow2
9A.WorkA.Work1.2
10 Functional Location Select Functional Location A - X - W
11 Work Center Select Work Center EM015

Perfect! But we need to insert resources within the order...

How can I do this

In the operations guide, the user can select a specific operation to insert resources such as material, personnel, tools, images, plans and PPE's.

Material Guide

In the materials guide, the user can view or insert all materials in the order. Also, insert new materials, insert the amount spent and edit the planned amount.

Sequor Platforma Site

Nr.FieldDescriptionSample
1 Material Sequence Material Sequence 0010
2Material NumberEnter Material NumberMT0018
3 Description of material Description of material Oil Filter
4 Unit of Material Unit of measure of material PC
5 Quantity Insert material planned to spend 100
6 good R. Insert the amount of good materials used ​​ 80
7 Scrap Enter the amount of scrap materials spent 5
8 Repair Enter the amount of repair materials spent 5
9 Surplus Enter excess quantity from plan -10

Inserting a Material into the Operation.

Sequor Platforma Site

Personnel guide

In the Personnel guide, the user can view or insert the entire Personnel of the order.

Sequor Platforma Site

Nr.FieldDescriptionSample
1Personnel SequencePersonnel Sequence0010
2Personnel NumberEnter Personnel NumberEM021
3Personnel DescriptionPersonnel DescriptionEletrical Maintener
4QuantityEnter Personnel planned to spend10
5Quantity M.Enter Material M5
6ACT. QTYEnter Quantity ACT5
7Time. QTYEnter Time ACT5
8Time UnitSelect unit of measurement of timeHours
9Time UNEnter Time UN
10Time ExtraEnter Quantity of time extra2.5

Inserting personnel into the operation.

Sequor Platforma Site

Guia PRT

In the PRT guide, the user can view or insert all order Productive Resource and tools.
PRT could be: Image, Ground Plan, Tool (equipment), PPE (equipment) or Tasklist, separated with 3 differents behaviors.

Image and Ground Plan

Sequor Platforma Site

Nr.FieldDescriptionSample
1PRT SequencePRT Sequence0010
2Type CodeSelect a PRT TypeImage
3Type DescriptionType DescriptionImage
4Long DescriptionEnter with Long Description
5PRT DescriptionEnter with PRT DescriptionPhoto of process
6Insert/Edit imageInsert/Edit image

How to insert Image

Click the button to insert images to the characteristics of your forms. It is possible to draw over the images, in addition to adding text, markers and more. Added items are vector and layered, which allows you to undo actions without losing previous work.

Sequor Platforma Site

Sequor Platforma Site

Tasklist

Sequor Platforma Site

Nr.FieldDescriptionSample
1PRT SequencePRT Sequence0010
2Type CodeSelect a PRT TypeTasklist
3PRT DescriptionEnter with PRT DescriptionTasklist used here
4Long DescriptionEnter with Long Description

Wow cool! I see that I can insert resources within an operation, but I can insert them within the order, how do I ??

What is the difference between inserting resources in order and in operation ???

Example:

  • The team will spend two bags of screws, it makes no sense to control how much will be spent on each operation. Just know the consumption of the order.
  • The team will spend a new bomb (specific material) in a specific operation. It is important to know which operation.

It is important to know that all feature features will be summed in order, plus materials entered in order. Example:
Inserted in operation A: 2 screw bags
Inserted in operation B: 1 screw bag
Inserted in order: 1 screw bag

Order Summary: 4 Screw Bags

Sequor Platforma Site

Release Order

Sequor Platforma Site

How to Release or Change the Status of an Order:
Releasing the Order is the process to “send” the Orders created in the Web application to the Mobile application and thus, they can be executed in the field. For more details, see the Sequor MTC Mobile Manual.

After accessing the Sequor MTC Order Release app, the user will enter the Grid / List mode, which lists all the Release Order entries, giving the user the ability to select an order and dispatch to Execution in the Mobile application.

To release an order:

  • 1 - select the desired record by clicking on the respective check box ,
  • 2 - click the button to open the Order Status Change Screen

Sequor Platforma Site

  • 3 – Select the desired option

    • Release Order - Releases the order for Execution
    • Cancel Order - Cancels the order and can no longer resume this order
    • Close Order – Closes the order and can return to a new schedule
    • Complete Order - Fully executed and can no longer resume this order
    • Pause Order – Pauses during order execution
    • Run Order - Start / Resume Running Order
    • Post Order - Post / Make the order available for planning
    • Stop Order – Pause order to be rescheduled
    • Complete Order Technically - Partially ends an order and can no longer resume it.
  • 4 - Click on to confirm your selection.

How to dispatch an order to mobile

Sequor Platforma Site

remarque

After accessing the Order Header Sequor MTC app, the user will enter Grid/List mode, which lists all Order Header entries, giving the user the ability to create a new entry or edit an existing one.

  • Select an order
  • Select the status for "Dispatch Order"
  • Press "Change order status"

This sequence of actions will release the order to be sent to the mobile app.

Material Quality

When in the field and the material received to carry out the activity has a problem, there is a function to report what happened - Material Quality / equipment. (This functionality is the same for material and equipment).

remarque

As an example case, the material flow will be presented, repeating itself in the same way in the case of equipment. This functionality is intended to assist in the information on materials that may undergo repairs or be scrapped. You can enter data such as "problem", "root cause" and "solution".

Sequor Platforma Site

In the material section, by clicking on the , the material quality notes screen will appear.

On this screen, fill in the fields of the note description, the quantity of materials with a quality problem, as well as the problem that occurred, its root cause and the solution used.

Sequor Platforma Site

To select the problem, root cause and solution, just click on the where the justifications for each field will be pre-registered. Finally, you can assign on the buttons if it is a case of (rework) or if it is a case of (scrap).

Sequor Platforma Site

Along with the material screen, the observation that there is a description of material quality will be pointed out.

When there is an entry, on the WEB screen in the material field, the will turn yellow.

Sequor Platforma Site

Making it easy for the planner to identify that there is a quality record of material.